Purchase Orders > Landed Cost Tracking > Reports > Shipment Tracking Report

Shipment Tracking Report

You use this program to list the details of Landed Cost shipments that are current, completed or archived.

Report Options

Field Description
Report type  
Current shipments

Select this to generate a report only for shipments that have not yet been received into stock.

[Note]

By default, the values displayed in the Actual cost and GRN value columns are displayed as zero because the report only reflects shipments against which no receipts have been captured.

You can, however, select the Assume total receipt when calculating actual cost option if you want to show values in the Actual cost and GRN value columns as if the total shipment had been received.

Received shipments

Select this to generate a report only for those shipments that have been received into stock.

Shipments that have been received into inspection are included only if you have processed a partial receipt into stock.

Archived shipments Select this to generate a report for only those shipments which have been archived.
Shipment content notes

Select this to generate a report showing the merchandise lines of current shipments.

It does not list any cost elements or shipment totals.

The contents note can be used by the warehouse staff to check the shipment before it is received into stock.

Options  
Use supplier xref for expected merchandise cost

Select this to calculate the Expected cost of a merchandise line based on the purchase order quantity multiplied by the LCT merchandise price defined against the supplier.

You assign the LCT merchandise price against the supplier using the Browse on Supplier Stock Code Cross Ref program. If you do not select this option, then the actual cost and GRN value printed for a merchandise line equals the Expected cost.

Assume total receipt when calculating actual merchandise cost

This applies when you select Current shipments at the Report type field.

Select this if (against merchandise lines) you want to print values in the Actual cost and GRN value columns as if the total shipment quantity had been received into stock.

[Note]

The GRN value column is displayed only if you indicated that the GRN system is required (Purchase Orders Setup - GRN tab).

Assume expected element value when actual element value is zero This applies when you select Current shipments at the Report type field.

Select this if you want the expected value of the element to be printed in the Actual value column if no invoices have been processed against the element and the actual cost is zero.

Selection criteria

Field Description
Vessel selection

Indicate the vessel(s) for which you want to generate the report.

You can browse on the vessel selections using the Browse on Vessels program.

Date selection

The date required depends on the Report type you selected.

If you selected to print the Report types: Current shipments or Shipment contents note, then you need to enter the required Arrival dates.

[Note]

This option ignores the estimated arrival date. Therefore, if an arrival date for the vessel was not entered, then the shipment is not included in the report.

If you selected to print the Report types: Received shipments or Archived shipments, then you need to enter the Receipt dates required.

Indicate the arrival/receipt date(s) for which you want to generate the report.

You can browse on Archived shipment references using the Browse on Archived Shipments program and on other shipment references using the LCT Shipment Reference Query program.

Shipment reference selection Indicate the shipment reference(s) for which you want to generate the report.

Output Options

These options enable you to apply a theme to the report and to define multiple output destinations for the report once it has been compiled (SRS Output Options).

Report Details

The report lists the cost elements attached to each purchase order line and accumulates the expected and actual costs against a shipment. The total for each line is then compared to the current inventory cost, or to the last cost if you are using FIFO or LIFO costing. The actual cost is calculated as the merchandise expected cost (price on purchase order multiplied by the quantity) divided by the quantity ordered multiplied by the quantity received. If the GRN suspense system is required (Purchase Orders Setup - GRN tab) then the GRN value will equal the actual cost.

When you process a shipment for a foreign currency supplier, the foreign value of the purchase order line is displayed in the supplier's currency next to the exchange rate. The supplier's currency code is printed next to the supplier code.

Where a fixed exchange rate was not used for a shipment, the exchange rate printed on the report is the current exchange rate as per the exchange rate table (Browse on Currencies). The merchandise cost is, however calculated at the entry rate. This is because the merchandise cost local value is calculated at the time the purchase order is attached to the shipment and this is the value reflected on the report. The report does not recalculate the merchandise cost local values based on the current exchange rate.

If an actual arrival date was entered for the vessel using the Browse on Vessels program, then this date is printed in the Est arrival date column. If no actual arrival date was entered, then the estimated arrival date is printed in the Est arrival date column.

The merchandise value on the report will only equal the value of the corresponding purchase order if all of the following are true:

  • all the purchase order lines are on the shipment
  • you have not change the quantity, discount, price, etc of any line
  • You have not altered the exchange rate