You use this program to view a graphical representation of the load assigned to a work center (i.e. reserved capacity, free capacity and capacity overloads).
The graph is scaled horizontally according to the capacity unit of measure defined against the work center, and vertically according to the capacity calendar dates defined against the work center.
When the Capacity Profile Graph program is accessed from Requirements Planning > Manual Scheduling > Load Levelling, then you are viewing snapshot information and the heading changes to Snapshot - Capacity Profile for Work Center.
Field | Description |
---|---|
Edit | |
Capacity Calendar | Select this to use the Capacity Calendar Maintenance program to view or define daily capacity records for each individual work center. |
Include | This option is only enabled when the Capacity Profile Graph program is accessed from Requirements Planning > Manual Scheduling > Load Levelling. |
Suggested Jobs | Select this to include suggested jobs in the capacity profile. |
Existing Jobs | Select this to include existing jobs in the capacity profile. |
Options | |
Preferences | You use this option to indicate the graphing preferences you require. |
This screen is displayed when you select the Preferences from the Options menu.
Field | Description |
---|---|
Number of days to view | Indicate the number of days for which you want to display pegging information. |
OK | Select this to save the preferences against your operator code. |
Cancel | Select this to save the preferences for the current run of the program only. |
This pane displays a graphical representation of the load assigned to the selected work center.
Field | Description |
---|---|
Work center |
|
Description | This indicates the description for the work center. |
Cell id | This indicates the work center's cell id, which is used within the Advanced Planning & Scheduling system. |
Cost center | This indicates the cost center to which the work center belongs. |
Units of measure |
|
Productive units |
|
Number of work operators | This indicates the number of operators available at the work center. |
Field | Description |
---|---|
Available | This indicates the capacity available as defined against the work center. |
Reserved | This indicates the planned capacity as defined against the work center. |
Over | If the planned capacity is greater than the capacity available, then this indicates the overloaded planned capacity after subtracting the available capacity from the planned capacity. |
Free | If the capacity available is greater than the planned capacity then this indicates the remaining capacity after subtracting the planned capacity from the available capacity. |
The information displayed in this listview relates to the line currently highlighted in the Capacity Profile listview.
Field | Description |
---|---|
Maintain Job | Select this to use the Job Entry program to maintain the job currently displayed in the listview. |
Job Graph | Select this to use the WIP Job Allocation Graph program to view a graphical representation of all operations allocated to the job. |
Query Job | Select this to use the WIP Query program to view detailed information on the job. |
Zoom on Operation | Select this to use the Labor Allocations program to view operation allocations for the job. |
Recalculate | You use this option to recalculate the cumulative capacity required. However, whenever you maintain a job or query a job, the entire capacity pegging is automatically reloaded thus correctly incrementing the cumulative capacity required. You should therefore not need to use this option. |
When the Capacity Profile Graph program is accessed from Requirements Planning > Manual Scheduling > Load Levelling, then you are viewing snapshot information and the heading of this listview changes to Snapshot - Capacity Pegging.
The Capacity Profile Graph program can be accessed by: